![]() |
|
|
www.southgatearc.org
|
|
![]() |
|
The S band unit
in its enclosure
|
The transmitter unit is built into a beautifully machined and finished aluminium box provided by the University of Wroclaw who have also developed the three way power splitter and the experimental patch antennas.
Except for the TNC, which is a commercial TNC 7, the whole unit has been designed and built from scratch by the team. There are five boards. The exciter from Sam G4DDK, the PSU from David G0MRF, the command & control board and the sensor board from Jason G7OCD and the 3W PA from Charlie G3WDG (an identical unit to that flying in AO51)
The unit was first "delivered" to ESTEC early in November 2004 but further work on the wiring was needed and it was then returned to them again at the end of the month. At this stage the first actual amateur call was put through the satellite in the clean-room from the "control room" next door.
"The Ground Station"
![]() |
The unit then remained at ESTEC and was regularly exercised to download data via the temporary ground station that had been provided to them by Howard G6LVB.
During February it became clear that the data rate from the OBC to the TNC needed to be changed to accommodate other mission requirements. An AMSAT team went over to rewire and reconfigure the unit and success was quickly achieved.
![]() |
|
The joy of a successful
baud rate change
|
We then went on to apply the conformal coating to all the PCBs (except around the RF parts). At this stage disaster struck as the somehow some of the coating found its way right inside one of the filter assemblies - result no RF output!
The unit was then brought back to the UK for "repair" but quickly returned again during the first week of March by Sam and David.
They were able to demonstrate the unit working again and also helped the SSETI team solve a power limiting problem which caused the unit to be switched off for 150ms every time it was commanded on - not helpful when trying to transmit short packets.
Here is an extract from part of the SSETI Express Integration logbook for 2nd March 2005:
ESA_Neil, AMS_David and AMS_Sam power up the OBC, UHF and S-BAND for the purposes of testing.
- The initial power consumption of S-Band FM seems good
- The carrier is brought up successfully with the usual command
- The DTMF telemetry is turned on and received without issue
- The unit is switched to data config and data is transmitted without
issue
- The carrier is brought back down
- The DTMF telemetry is turned on and received without issue
- The unit is switched to data config and data is transmitted without
issue
- Transponding is tested without issue
MILESTONE 25: The S-Band sub-system is declared flight-ready.
![]() |
|
Neil Melville -
SSETI Express Project Manager captured on the Webcam on 8th March
2005 - admiring the satellite under construction in the clean room
at ESTEC!
|
Actually the S band transmitter is the FIRST sub-system to be declared flight-ready!
It has been a great experience for the AMSAT-UK team to be working with
both the ESA experts and also the enthusiastic students - a number of
whom have expressed the intention to get an amateur licence for themselves!
It is a steep learning curve for them and for us - although we have been
flattered in one presentation recently given by Neil Melville - the Project
manager, which includes the text "Radio amateurs know what they are
talking about"
What happens next?
A total of 150 solar cells, in ten strings of 15, are currently being laid onto the external panels of the satellite and we anticipate that these should be sufficient to enable the U/S transponder to work with the carrier up on a near 24/7 basis.
The flight model of the satellite will be completed over the next few weeks and will be subjected to the usual vibration tests and also thermal vacuum tests. Hopefully these tests will be completed without incident or problem.
The launch date is still not confirmed but should be late this summer.
The SSETI team will be providing full telemetry decoding information and will be encouraging us to provide downlinked telemetry data for them from around the world. They only have two ground stations of their own available and the software does not provide the "whole orbit data" that we are used to. Our worldwide network is certainly a unique facility and this data collection exercise will be good PR for the amateur satellite movement. ESA will be providing a prize for the amateur who provides them with the most. Full details will be available on the sseti website well before launch.
It is expected that the on board experiments should be completed within a matter of a couple of months from launch and after that the transponder can be placed into service. There is still a long way to go before that happy state becomes a reality and we have to remember that this is a high risk project - but if we don't try
References:
Full information about the project is available at the regularly updated www.sseti.net website. This includes the complete integration logbook mentioned above. It is a big file but makes very good reading for satellite enthusiasts!
The webcam: http://sseti.gte.tuwien.ac.at/WSW4/express4.htm
Downloads: http://sseti.gte.tuwien.ac.at/WSW4/express_downloads.htm
Space Colloquium
Members of the AMSAT-UK team who produced the S Band transmitter will
be giving a presentation on SSETI Express at the AMSAT-UK Space Colloquium.
This will be held at the University of Surrey in Guildford from 29 - 31st
July.
All Amateurs and SWL's are welcome to attend the event.
For further details contact the secretary Jim Heck G3WGM
Tel: 01258 453959
Email: g3wgm@amsat.org
Website: http://www.uk.amsat.org/
|
|
| |
|
| Home
| For
Sale & Wanted | Tell
a friend | Guestbook
| Cast Your Vote | Newsboard
| Amateur Radio
Forum | Links | Diary
Dates | | Games | SWLs | 'How To' Guides | Humour | Data Comms | Lottery | Amateur TV | Contests | Can You Help? | Contact Us | 10 Metres | | Clubs Worldwide | Subscribe to our Newsletter | | |
|
| |